2015 Chip Seal Program

Project Description


This project consists of placing an oil and rock chip surface, as well as minor roadside maintenance of ditches and shoulders, on approximately 20.96 miles of various County-maintained roads. All work will be done within the existing right-of-way. Road segments to chip seal include but may not be limited to:
  • Annie Drive - all (1.17 miles)
  • Avern Way - all (0.17 mile)Scotts Valley Road - Willow Valley to pavement (0.5 mile)
  • Back Bone Road - Cruzon Grade to Derbec (2.59 miles)
  • Betty Way - all (0.11 mile)You Bet Road - Bridge to lake (5.57 miles)
  • Cathy Drive - all (0.09 mile)
  • Clover Valley - Brewer Road to end of County road (0.11 mile)
  • Clover Valley CSA - all (0.84 mile)
  • Cruzon Grade - all (3.5 miles)
  • Derbec Road - Back Bone Road to North Bloomfield (0.8 mile)
  • Eva Way - all (0.04 mile)
  • Fay Road - Rainbow Road to end of County road (0.35 mile)
  • Janet Way - all (0.08 mile)
  • Joey Court - all (0.09 mile)
  • John Way - all ( 0.22 mile)
  • Judith Court - all (0.05 mile)
  • Kenneth Court CSA - all (0.10 mile)
  • Nancy Way - all (0.31 mile)
  • North Bloomfield - Derbec to Relief Hill Road (1.3 miles)
  • Pamela Way - all (0.12 mile)
  • Rainbow Road - Carrie Drive to end of County road (0.37 mile)
  • Rainbow Road CSA - all (1.47 miles)
  • Red Dog Road - You Bet to end of chip seal (1.06 miles)
  • Sandra Court - all (0.05 mile)

Funding


  • HUTA, New HUTA, Fed Forest

Total Budget


  • $1,305,766

Current Status


  • Construction scheduled for 2015

CEQA


  • Categorical Exemption pending