Donner Pass Road Construction Updates

◄ Back
June 2, 2020 4:32 PM

Donner Pass Road Construction

This project consists of road rehabilitation and shoulder widening on 6.5 miles of Donner Pass Road beginning at the Soda Springs exit and ending at the Truckee town limit east of the summit. A typical road section will consist of two 11-foot lanes with 4-foot shoulders plus safety edges, except in the downhill direction on the east side due to topographical constraints. The project will also improve recreational and sightseeing access, with enhanced parking on the east side of the summit that connects to rock climbing, hiking, and biking amenities, as well as to historic and prehistoric features. Bicycling conditions will be improved with bike lanes in both directions on the west side and in the uphill direction on the east side. Enhanced pullouts and parking areas include the Rainbow Bridge parking lot, School House pullout, Star Wall pullout, Snow shed North and South pullouts, Space Wall pullout, and Black Wall pullout. During the winter the widening will also provide additional snow storage and improve access to winter recreational destinations. Nevada County received California Federal Lands Access Program (FLAP) funding for this project in 2015. The project is being managed and delivered by the Central Federal Lands Highway Division (CFLHD).

Facebook Twitter Email

Latest Update:

September 16, 2020 3:03 PM

The Donner Pass road closure will be extended from Rainbow Bridge to the summit on weekdays from 7:00 AM beginning September 21st through 5:00 PM October 2nd in addition to the existing closure from Rainbow Bridge to the Town of Truckee limits. The road will be open on weekends as usual.

Prior Updates

June 18, 2020 4:09 PM

Starting Monday 6/22, expect one-lane traffic control with 20-min delays from Donner Summit east to Town of Truckee limits.

Starting Monday 6/22, expect one-lane traffic control
June 2, 2020 4:36 PM

Construction activities have begun. Expect single lane closures as crews perform utility locating and survey layout. Delays should be minor, and flaggers will be present to assist motorists and cyclists through the project. This schedule will be updated as more information becomes available.